Project: Smithtown Central School District 2000 Bond Issue     


Project Schedule 2000 through 2004

 

Total Square Footage: 163,000

 

Budget: 142 Million

 

In the year 2000, McClave Engineering PC formed a joint venture with Turner Construction Management. The joint venture has created a dynamic company that can manage a verity of construction disciplines. Currently McClave/Turner CM is managing the 142 million dollar Smithtown Central School District (SCSD) 2000 bond issue. The scope of this management project covers many facets of both new construction and the renovation of existing buildings.

 

Projects completed to date:

  • 2000: Managed the installation of a new fiber optic wide area network linking 16 schools and three management facilities.
  • 2000: Managed the installation of six portable classrooms.
  • 2001-2003: Managed 85,000 SF of the new construction.
  • 2001-2003: Managed 15,800 SF of renovation to existing SCSD facilities.
  • 2001-2003: Managed the installation of nine new transformers.
  • 2001-2003: Managed the installation of a local fiber optic network within nine elementary schools.

All of the above projects came in on time, and within the budget constraints set forth by the SCSD.

 

Current Projects:

  • 2003-August 2004: Managing 35,000 SF of new construction.
  • 2003-August 2004: Managing 20,000 SF of renovation to existing SCSD facilities.
  • 2003-August 2004: Managing the installation of a local fiber optic network within three middle schools.

All projects are currently on schedule and will be occupied by the school district in August 2004